The Emergency Management Department of the Velocity Interoperability Network publishes statistics on the matters by which its work can be judged: incidents recorded and how long they took to close, exercises held and the findings they produced, the number of trained responders, the currency of the plans in the register, and the number of addresses registered to receive Network alerts.

This first release covers the transition period from 10 August to 5 September 2026, during which member organisations transferred their emergency arrangements to the Department, and records the position at establishment on 6 September 2026. The figures are drawn from the logs kept at each site under the interim arrangements, from the exercise records, and from the Department's own registration records. Figures for the transition period are provisional and will be revised in the next release where late returns are received.

Two cautions should be read with the figures. First, the interim logs were not kept to a common standard before 10 August 2026, so no comparison with earlier periods is possible. Second, an incident is counted when it was recorded, not when it began; three of the incidents below had been running for some hours before a log was opened.

The position at establishment.

41
Incidents recorded across the six principal sites in the transition period
24
Emergency plans in the register at establishment, all reviewed within six weeks
186
Members of site response teams trained and on call at their own sites
11,900
Addresses registered to receive Network alerts at establishment

Incidents by cause. Median duration is measured from the opening of the log to the closure of the incident. The structural defect at Eastfield Campus was closed after thirty-one hours because the building was kept out of use pending inspection; a single incident of that length is the reason the table gives the median rather than the mean.

Incidents recorded, 10 August to 5 September 2026
CauseIncidentsClosed same dayMedian durationPlan applied
Failure of the electrical supply16152 h 10 mEP/H/04
Loss of network connectivity983 h 05 mEP/H/05
Severe weather and high wind654 h 40 mEP/H/02
Flooding and surface water426 h 25 mEP/H/01
Fire alarm activation330 h 35 mEP/H/03
Failure of the water supply215 h 15 mEP/H/06
Structural defect reported1031 h 00 mEP/H/08
All causes41343 h 20 m

Incidents by site. The Network alert levels do not come into force until 7 September 2026. The level given below is the level at which the interim site arrangements were operating, mapped onto the Network scale so that the period can be compared with those that follow; no site reached the equivalent of Emergency. Findings arising are those recorded at incident review and carried into a plan.

Incidents by site, 10 August to 5 September 2026
SiteIncidentsLasting over 6 hoursHighest level reachedFindings arising
Central Exchange123Advisory1
Northgate Relay81Advisory1
Southbank Terminal71Alert2
Eastfield Campus61Advisory1
Westbrook Distribution Site51Alert1
Meridian Court32Alert1

Exercises and their findings. Nine exercises were held during the transition period. Exercise Meridian was the largest and the only one to involve two sites; its findings are set out in full on the Response page. Two exercises produced no findings; the Department regards this as a criticism of the exercises rather than a compliment to the plans.

Exercises held, 10 August to 5 September 2026
DateExerciseSiteScenario testedTook partFindings
27 August 2026Exercise MeridianMeridian CourtFlooding and power failure1483
20 August 2026Exercise WestbrookWestbrook Distribution SiteRelease of a hazardous substance642
18 August 2026Exercise SouthbankSouthbank TerminalFire in an occupied building961
17 August 2026Exercise EastfieldEastfield CampusEvacuation and assembly1121
14 August 2026Exercise Northgate INorthgate RelayLoss of network connectivity582
13 August 2026Exercise Central IICentral ExchangeContinuity of the Coordination Centre310
12 August 2026Exercise Central ICentral ExchangeAlerting and warning441
11 August 2026Table-top reviewCentral ExchangeDirection across two sites221
10 August 2026Table-top reviewCentral ExchangeRegister of plans and ownership180

Capacity at establishment.

9
Exercises held during the transition period, of which one involved two sites
11
Findings recorded at exercises, all carried into the plans concerned
83%
Incidents closed within the day on which they were reported
6
Site emergency controllers on duty from 7 September 2026, each with two deputies

Trained responders and plan currency by site. Every member of a site response team completed the Department's training during the transition period. The date given is the date on which that site's emergency plan was last reviewed.

Site response teams and plan currency at establishment
SiteTrained respondersOn call at any timeController and deputiesSite plan reviewed
Central Exchange481432 September 2026
Northgate Relay31931 September 2026
Southbank Terminal298328 August 2026
Eastfield Campus288326 August 2026
Westbrook Distribution Site298324 August 2026
Meridian Court21633 September 2026

Next release. The Department will publish statistics quarterly. The next release, covering the quarter ending 30 September 2026, will be published in October and will include the findings of Exercise Northgate II, to be held at Northgate Relay on 13 October 2026, together with the first figures for the time taken to warn a whole site against the five-minute standard.

The plans referred to above are listed on the Register of Emergency Plans page and the alert levels on the Network Alert Levels page. Enquiries about the figures, including requests for the definitions used, may be sent to contact@emergencies.gov.vin.